Studio · Hanga · programme

Programme resequencer · proposal tool

Rebuild the week around who is actually blocked.

Read the programme and yesterday’s site log. See which crews are waiting on which trade, and get a resequenced week for the project manager to approve. Nothing is sent to subcontractors.

01

Read the programme

CSV or XLSX with id, name, trade, start, duration, predecessors and crew. Optional: not_before (hard date) and contract_date. MS Project XML also works.

Example programme · fictionalEXAMPLE

Example programme · two-storey house, Tāmaki Makaurau (fictional)

29 tasks · 15 trades · starts Mon 7 Sep 2026 · 2 contracted dates · weekends and NZ public holidays are non-working

Durations, crews and dates are illustrative. It carries no rates.

02

Read the site log

The log reader runs on this device and matches each line to a task. You confirm every update before it is applied.

Site log by task · 0 entries for Thu 15 Oct 2026

Tasks with no entry are assumed to be on programme, but never past an unfinished predecessor. Showing work programmed around the log date.

T06 Level 1 floor and wall framing
Builder · programmed Wed 7 Oct–Wed 14 Oct · assumed done
T07 Roof framing
Builder · programmed Thu 15 Oct–Mon 19 Oct · assumed partly done 33%
T09 Windows and exterior doors
Window installer · programmed Thu 15 Oct–Fri 16 Oct · assumed partly done 50%
T11 Electrical rough-in, ground floor
Electrical · programmed Wed 7 Oct–Fri 9 Oct · assumed done
T12 Plumbing rough-in, ground floor
Plumbing · programmed Wed 7 Oct–Fri 9 Oct · assumed done
T13 Electrical rough-in, Level 1
Electrical · programmed Thu 15 Oct–Mon 19 Oct · assumed partly done 33%
T14 Plumbing rough-in, Level 1
Plumbing · programmed Thu 15 Oct–Mon 19 Oct · assumed partly done 33%
Proposed resequence for the project manager’s approvalExampleAwaiting approval · not sent

No trade is blocked today, but 16 tasks finish later than programmed.

Fri 16 Oct
Today (after log)
0
Crews waiting today
0
Can start today
Mon 7 Dec
Finish · +1 working days
2
Contract flags
03

Blocked trades

  • Roofer This week
    T08 Roofing waits on Roof framing (Builder, under way, 33%).
    Programmed Tue 20 Oct; can start Wed 21 Oct.
03b

Who is blocked

Filled: work holding others up. Outlined: crews waiting. Dashed: waiting on their own trade.

BuilderRoof framingUNDER WAY · 33%RooferRoofingWAITING · THIS WEEK
04

Resequence from today

Critical path from Fri 16 Oct: T07 → T08 → T17 → T19 → T20 → T21 → T22 → T23 → T25 → T26 → T27. Levelled to the people each trade has available, keeping every link, lag and hard date. Finish Fri 4 Dec as programmed, Mon 7 Dec proposed.

Task · trade
7 Sep14 Sep21 Sep28 Sep5 Oct12 Oct19 Oct27 Oct2 Nov9 Nov16 Nov23 Nov30 Nov7 Dec14 Dec
T01 Site establishment and fencingBuilder
done
T02 Site cut and excavationEarthworks
done
T03 Underground drainageDrainlayer
done
T04 Foundations and slab pourConcrete
done
T05 Ground floor framingBuilder
done
T06 Level 1 floor and wall framingBuilder
done
T07 Roof framingBuilder · critical
33% · +1d finish
T08 RoofingRoofer · critical
+1d
T09 Windows and exterior doorsWindow installer
50% · 0d finish
T10 Building wrap and cavity battensCladder
T11 Electrical rough-in, ground floorElectrical
done
T12 Plumbing rough-in, ground floorPlumbing
done
T13 Electrical rough-in, Level 1Electrical
33% · +1d finish
T14 Plumbing rough-in, Level 1Plumbing
33% · +1d finish
T15 Meter board and mains supplyElectrical
T16 Hot water cylinder and external plumbingPlumbing
T17 Pre-line inspectionCouncil inspection · critical
+1d
T18 Weatherboard claddingCladder
+1d
T19 InsulationInsulation · critical
+1d
T20 GIB liningGIB fixer · critical
+1d
T21 GIB stoppingStopper · critical
+1d
T22 Interior paintingPainter · critical
+1d
T23 Kitchen and joinery installKitchen joiner · critical
+1d
T24 Electrical fit-offElectrical
T25 Plumbing fit-offPlumbing · critical
+1d
T26 Floor coveringsFlooring · critical
+1d
T27 Code compliance inspectionCouncil inspection · critical
+1d
M1 Closed in (weathertight)Milestone
+1d
M2 Practical completionMilestone · critical
+1d
Today

What moves (17)

TaskTradeProgrammedProposedStart movesWhy
T07 Roof framing criticalBuilderThu 15 Oct–Mon 19 OctFri 16 Oct–Tue 20 Oct—Under way; finish follows what is left
T08 Roofing criticalRooferTue 20 Oct–Fri 23 OctWed 21 Oct–Tue 27 Oct+1dWaits on Roof framing
T09 Windows and exterior doorsWindow installerThu 15 Oct–Fri 16 OctFri 16 Oct–Fri 16 Oct—Under way; finish follows what is left
T13 Electrical rough-in, Level 1ElectricalThu 15 Oct–Mon 19 OctFri 16 Oct–Tue 20 Oct—Under way; finish follows what is left
T14 Plumbing rough-in, Level 1PlumbingThu 15 Oct–Mon 19 OctFri 16 Oct–Tue 20 Oct—Under way; finish follows what is left
T17 Pre-line inspection criticalCouncil inspectionTue 27 Oct–Tue 27 OctWed 28 Oct–Wed 28 Oct+1dWaits on Roofing
T18 Weatherboard claddingCladderTue 27 Oct–Thu 5 NovWed 28 Oct–Fri 6 Nov+1dWaits on Roofing
T19 Insulation criticalInsulationWed 28 Oct–Thu 29 OctThu 29 Oct–Fri 30 Oct+1dWaits on Pre-line inspection
T20 GIB lining criticalGIB fixerFri 30 Oct–Fri 6 NovMon 2 Nov–Mon 9 Nov+1dWaits on Insulation
T21 GIB stopping criticalStopperMon 9 Nov–Fri 13 NovTue 10 Nov–Mon 16 Nov+1dWaits on GIB lining
T22 Interior painting criticalPainterMon 16 Nov–Mon 23 NovTue 17 Nov–Tue 24 Nov+1dWaits on GIB stopping
T23 Kitchen and joinery install criticalKitchen joinerTue 24 Nov–Thu 26 NovWed 25 Nov–Fri 27 Nov+1dWaits on Interior painting
T25 Plumbing fit-off criticalPlumbingFri 27 Nov–Mon 30 NovMon 30 Nov–Tue 1 Dec+1dWaits on Kitchen and joinery install
T26 Floor coverings criticalFlooringTue 1 Dec–Thu 3 DecWed 2 Dec–Fri 4 Dec+1dWaits on Plumbing fit-off
T27 Code compliance inspection criticalCouncil inspectionFri 4 Dec–Fri 4 DecMon 7 Dec–Mon 7 Dec+1dWaits on Floor coverings
M1 Closed in (weathertight)MilestoneFri 23 OctTue 27 Oct+1dWaits on Roofing
M2 Practical completion criticalMilestoneFri 4 DecMon 7 Dec+1dWaits on Code compliance inspection
05

Idle cost

Cost uses only the rates you enter here, per person-hour. Where there is no rate, you see hours and no dollar figure.

Set to 8 to start with. Change it to match your site.
TradePeople availableNZD per person-hour
Builder
Earthworks
Drainlayer
Concrete
Roofer
Window installer
Cladder
Electrical
Plumbing
Insulation
GIB fixer
Stopper
Painter
Kitchen joiner
Flooring

This week, if crews turn up as programmed

CrewPeople × daysHoursCost
Roofers
Roofing · waiting on Roof framing
3 × 124 henter a rate

24 h of idle crew time. Rebooking crews to the proposed dates avoids it.

Logged yesterday

No idle hours in the site log.

No rate entered for Roofer, so those hours are not costed.

06

Contract flags

Moves · inside contract date
Closed in (weathertight)Programmed Fri 23 Oct → proposed Tue 27 Oct (+1 working day). Contract date Wed 28 Oct 2026: 1 working day to spare.
Moves · inside contract date
Practical completionProgrammed Fri 4 Dec → proposed Mon 7 Dec (+1 working day). Contract date Thu 10 Dec 2026: 3 working days to spare.

A flag needs the project manager’s attention before approval. It does not change the contract or notify anyone.

07

Project manager’s decision

Approving or rejecting adds a line to the record log. It does not send, book or notify anyone.

Record log

No decisions recorded yet on this device.